Projects
Hotel Diplomat Zagreb
Street
Horvatova ul. 35B
Town
Zagreb
Achieved energy savings
869.084 kWh/per year or 74.89%
Reduction of CO2 emissions
282,07 t/year
Performed works
- Work in progress
- Preparatory works and scaffolding
- Concrete work
- Improving the existing heating, cooling, and ventilation system with a heat pump
- Solar collectors for DHW production
- Renovation of part of the envelope of the heated space of the building
SZ Sinj
Street
Put Piketa
Town
Sinj
Year of construction
2021.
Performed works
- Installation of Layher Blitz scaffolding
- Installation of the Facade systems ETICS (d=10cm)
- Installation of finishing PVC profile with mesh (APU)
- Installation of water drip PVC profiles
- Supply of materials and application of deep nano impregnation on all concrete surfaces
Projekt Gruž
Street
Ante Starčevića 2
Town
Dubrovnik
Year of construction
2021.
Performed works
- Installation of the Facade systems ETICS (d=10cm)
- Installation of finishing PVC profile with mesh (APU) on the joinery
- Installation of water drip PVC profiles at drip points
- Installation of external RAL waterproofing tape on joinery
Osnovna škola Ivo Kozarčanin
Street
Tomislava Bogića 2
Town
Hrvatska Dubica
Year of construction
2019.
Achieved energy savings
113.313,00 kWh/per year or 52,2%
Reduction of CO2 emissions
98,72 t/year
Performed works
- Excavations and landscaping
- Installation of the Facade systems ETICS with mineral wool slabs (d=14 cm), final decorative plaster
- Waterproofing of the flat roof with TPO roof membrane
- Installation of PVC joinery (RAL assembly)
- Reconstruction of the heating system – supply and installation of new radiators and accompanying equipment
- Installation of photovoltaic power station (connected power: 19.61 kW; expected annual production: 19,900 kW; A = 121.12 m2)
Dubrovačka 2
Street
Dubrovačka 2
Town
Rijeka
Year of construction
1974.
Achieved energy savings
602,973.80 kWh/per year or 55.50%
Reduction of CO2 emissions
159,97 t/year
Performed works
- Installation of the Facade systems ETICS
- Installation of a steel wheelchair ramp with a handle
- Construction of a reinforced concrete slab
- Installation of thermal insulation on a flat roof
- Construction of horizontal waterproofing with a vapor barrier
Učenički dom Split
Street
Matice Hrvatske 13
Town
Split
Year of construction
1972.
Achieved energy savings
328.437,94 kWh/per year or 89,17%
Reduction of CO2 emissions
25,73 t/year
Performed works
- Installation of the Facade systems ETICS
- Installation of new window sills
- Installation of flush air condensate
- Cleaning, sanding and repairing a dilapidated fence