Projects

KBC Križine

KBC Križine

Street

Šoltanska ulica 1

Town

Split

Year of construction

1965.

Open gallery
Učenički dom Split

Učenički dom Split

Street

Matice Hrvatske 13

Town

Split

Year of construction

1972.

Achieved energy savings

328.437,94 kWh/per year or 89,17%

Reduction of CO2 emissions

25,73 t/year

Performed works

  • Installation of the Facade systems ETICS
  • Installation of new window sills
  • Installation of flush air condensate
  • Cleaning, sanding and repairing a dilapidated fence

Open gallery
Ulica kardinala Stepinca

Ulica kardinala Stepinca

Street

Ulica kardinala Stepinca

Town

Dubrovnik

Year of construction

2019.

Performed works

  • Installation of the Facade systems ETICS

Open gallery
SZ Gornja Glavina

SZ Gornja Glavina

Street

Gornja Glavina

Town

Imotski

Performed works

  • Installation of the Facade systems ETICS

Open gallery
Stadion HNK Zmaj

Stadion HNK Zmaj

Street

Stadion HNK Zmaj

Town

Makarska

Year of construction

1979.

Achieved energy savings

121.947,83 kWh/per year or 61,31%

Reduction of CO2 emissions

36,53 t/year

Performed works

  • Installation of the Facade systems ETICS
  • Installation of PVC joinery
  • Masonry of the parapet under the positions of the newly installed carpentry
  • Waterproofing of the tribune base
  • Installation of new seats in the stands
  • Rehabilitation, painting and protection of the existing metal fence
  • Installation of double wall cladding of plasterboard

Open gallery
Šibenska 1

Šibenska 1

Street

Šibenska 1

Town

Rijeka

Year of construction

1961.

Achieved energy savings

224.281,87 kWh/per year or 86,00%

Reduction of CO2 emissions

3,90 t/year

Performed works

  • Installation of Layher Blitz scaffolding
  • Installation of the Facade systems ETICS
  • Installation of new granite benches
  • Installation of tin covers on the roof attic
  • Installation of flush air condensate
  • Installation of PVC joinery
  • Installation of new ALU shutters

Open gallery
Put za forticu 6a i 6b

Put za forticu 6a i 6b

Street

Put za forticu 6a i 6b

Town

Rijeka

Year of construction

1995.

Achieved energy savings

50.920,39 kWh/per year or 68,00%

Reduction of CO2 emissions

19,54 t/year

Performed works

  • Installation of the Facade systems ETICS
  • Installation of new Bianco Cristal granite benches
  • Installation of new ALU joinery with a 5-chamber system
  • Installation of new ALU shutters with movable slats
  • Installation of Layher Blitz high-speed scaffolding during work

Open gallery
Nike Katunara 12

Nike Katunara 12

Street

Nike Katunara 12

Town

Rijeka

Year of construction

1968.

Achieved energy savings

349.345,05 kWh/per year or 75,00%

Reduction of CO2 emissions

2,18 t/year

Open gallery
Joakima Rakovca 13

Joakima Rakovca 13

Street

Joakima Rakovca 13

Town

Opatija

Year of construction

1961.

Achieved energy savings

59.634,15 kWh/per year or 71,00%

Reduction of CO2 emissions

14 t/year

Open gallery
Bribirska 7 i 9

Bribirska 7 i 9

Street

Bribirska 7 i 9

Town

Rijeka

Year of construction

1935.

Achieved energy savings

103.877,33 kWh/per year or 60,50%

Reduction of CO2 emissions

11,42 t/year

Open gallery